East Riding College
East Riding College is delighted with improvements to the lighting at its Bridlington campus and will significantly reduce annual running costs following a successful upgrade to LED technology – financed by Salix Finance.
Project overview
Energys Group LED upgrade set to deliver £34K annual savings for East Riding FE College at its Bridlington campus.
Return on investment is predicted to be just over four years and CO2 savings are calculated to be as high as 116 tonnes per annum.
Outcomes
- £34k annual energy savings
- 4.2 years return on investment
- Improved illumination
The project in detail
Annual £ saving
£34,000
CO2 per year saving
116 tonnes
Project Value
£144,000
Energy Reduction
81%
Finance
Salix Finance - College Energy Fund